WHILE the first stage of Redlands’ $57.4 million Wellington St-Panorama Drive upgrade has been completed, there is no certainty over when – or if – duplication will continue towards Cleveland.
Stage One, between Boundary Rd and South St at Thornlands, was completed in 2024.
In response to questions from Local Redland Bayside News, Council said only that duplication from South St to Russell St had been identified as a “potential future project” in its long-term capital works program, subject to approval and funding.
The response did not provide a construction timeframe, cost estimate or fresh funding commitment for the later work.
Stage One was officially opened in December 2024 after delivering a two-kilometre duplication from two to four lanes along Panorama Drive and Wellington St.
It included upgrades at the Ziegenfusz Rd-Panorama Drive and Panorama Drive-Wellington St intersections, a shared cycling and pedestrian path from Boundary Rd to South St, and a dedicated fauna underpass.
The project was promoted as a $57.4m three-level government investment, with Redland City Council contributing $41.7m, the Australian Government providing $15m through its Infrastructure Investment Program, and Queensland Government support for the shared path.
The first stage was approved by Council in September 2020.
While the original program referred to a second stage from South St to Russell St, the latest response does not break the remaining route into separate South St to Bay St and Bay St to Russell St stages.
Instead, Council has grouped the full South St-Russell St section as a future possibility dependent on competing capital works priorities and grants from other levels of government.
The corridor is a key north-south link for residents travelling between Thornlands, Redland Bay, Mount Cotton and Cleveland, with Council previously saying the upgrade would improve peak-hour travel times, ease congestion and boost safety.